Flamingo Point Center
Location: Miami Beach Florida
- We cut a trench that was 15 inches thick ( 300 sq ft ) and removed it.
- We also had to chip back 12 inches to tie into the rebar when poured back.
- Finally, we also poured back the slab.
“This project was very difficult due to many factors. The removal process alone was very difficult because our bobcat was not allowed inside because obviously it was inside the Building. Took lots of man power to get this one done”